Organization of processing of municipal solid waste alternative

Investment proposal
  

Name of the project

Organization of processing of municipal solid waste alternative

 

Main goals of project

Improving the ecological condition of the region through the processing and disposal of municipal solid waste, turning them into liquid (diesel) fuel and coal briquettes

Sphere /industry

Ecology

 

Implementation of schedule project

 

Location of the project

Tashkent region, Akhangaran district

 

Information about participants of the project:

– initiator

Ecologic Biologist Harakat LLC, Euro of those partners (Germany)

– co-executor (the lead sectorial of Ministry/authority/Department)

 

– creditor

 

Total costs of project

9.425 million euros ($ 9.678 million)

Prospective source of financing:

– own funds

 

– credits

 

– the required volume of direct foreign investments

2.175 million euros ($ 3 million)

Composition of main costs

 

Predictable of profitability

 

Predictable of payback period

3-5 years

 

Cash flows

 

Characteristics of the planned to production

 

Capacity of project/productivity

Recycling and disposal of 37,000 tons. MSW per year

 

Contribution to the project by the initiator

 

Current status of project

A memorandum and a contract for the supply of equipment with the German country 70% of direct investment has been signed

Information about the initiator of the project
 

Full name of the enterprises

Ekologik biologik harakat llc

 Requisites, email, contacts

+998933989162

Date foundation of enterprises

 

Statutory fund and

 

Structure of founders and distribution of shares

 

General information
  

Number and types of jobs created

50

Environmental impact statement (project EIS), which includes expected types and volumes of wastes, places of their utilization

Ecologicaly clean

Information about the land plot for the construction of the enterprise

2.0 hectares in CFY Ozodlik Ahangar district

Existing infrastructure

 

The required infrastructure

 

Upcoming construction and installation works

 

Design and estimate documentation

 

Power requirement (kWh), installed capacity (kWh or megawatt hour)

The need for electro-energy is only needed when starting a plant.

 

Demand for water (cub/m)

No water required

 

Gas demand (cu/m)

 

Market analysis, productions definition (works, services),marketing researches
  

Type of product

 

Annual production (ton. year)

 

Prospective markets sales and their shares:

Inner

 

Export

 

Coasts of products

 

Demand for raw materials (per year)

 

Provision of raw materials

 

Market volume

 

Expected market share

 

Arch-rivals

 

Main competitive advantage

 

Main target groups of consumers

 

The structure of sales according to target groups of consumers

 

 

 

 

 

 

Pricing strategy

 

Cost structure of the final product

 

Availability of patents, licenses, certificates in accordance with the current legislation

 

The presence of a formed database of potential customers with a confirmed willingness to purchase products

 

Presence of marketing research

 

Presentation component of the project

 

Additional information

 

Project risk

 
Production technology and parameters of main equipment
  

Depends on the investor’s preferences

Type of equipment

 

Country of origin

 

Performance

 

Cost

1.                   

Energy consumption

 

Installed capacity

 

Overall size of equipment

 

Weight of main equipment

 

Node of main equipment (lines)

 

Number of working hours per year

 

Duty cycle

 

Periodicity of the planned –warning repair (design and preparation works)

 

Number of people involved in the production process and their functions

 

STEP-BY-STEP, DESCRIPTION OF PRODUCTION TECHNOLOGY

(Show schematically)